Horse Barn Proposal Comparison Checklist

Print one copy per bid. Write the number each proposal gives for every line — or "excluded," "by owner," or "not stated." The bid with the most "not stated" entries is the one to call first, not the cheapest one.

Most horse-barn proposals are not comparable as written: one prices a shell, one prices a shell with stalls, one prices the whole job. Builders' own price pages list what they leave out — the cost guide quotes them. This sheet puts every bid on the same scope so the totals mean something.

A. The building (shell)

Line Bid 1 Bid 2 Bid 3
Footprint (W × L) and eave height
Construction type (post-frame / steel-frame / modular / kit)
Posts: treated laminated (retention level) or precast concrete columns; embedment depth; footing size
Truss spacing and design loads stated (wind mph, exposure, roof snow psf)
Roof and wall steel gauge; paint warranty years
Drip-control / condensation layer under roof steel (type, R-value)
Overhangs (which sides, how deep); porch or lean-to
End doors (size, sliding/overhead), walk doors, windows (count, size, grilles)
Eave and ridge ventilation openings; cupolas (count, size, powered?)
Wainscot / kick-plate on exterior
Interior liner panels or insulation (where)
Engineered, sealed drawings included? (required for post-frame in Johnson County, KS)
Shell subtotal

B. Concrete

Line Bid 1 Bid 2 Bid 3
Aisle slab: thickness, reinforcing, finish (broom)
Tack / feed / wash room slabs
Stall floors: concrete, or compacted stone base (depth)
Aprons at doors
Wash-stall trench drain and slope
Concrete subtotal

C. Equine fit-out

Line Bid 1 Bid 2 Bid 3
Stall count and size (e.g., 4 × 12 ft × 12 ft)
Stall fronts: brand/style, door type (sliding/hinged), grille spacing, lumber species and thickness
Partitions: height, lower solid height, upper grille or mesh
Dutch doors to exterior (count)
Stall mats (thickness, interlocking?) and base
Tack room (size, insulated, heated, ceiling)
Feed room (size, sealed floor, rodent-proofing)
Wash stall (size, non-slip floor, drain, hot water)
Hay storage: in-barn day supply only / separate building (priced?)
Waterers (brand, heated?) or hydrant locations
Fit-out subtotal

D. Sitework

Line Bid 1 Bid 2 Bid 3
Who does the pad (builder / excavator / owner)
Pad: strip topsoil, compact, rock depth, height above grade
Grading and drainage away from building; swales, French drains
Gutters and downspouts, discharge routed where
Rock excavation: allowance or unit price per cubic yard
Construction access and driveway rock; culvert
Dry-lot heavy-use pad at doors and gates
Final grade and seeding / restoration
Sitework subtotal

E. Utilities

Line Bid 1 Bid 2 Bid 3
Electrical service to barn: amperage, trench length, conduit, subpanel
Interior electrical: fixture count and type (sealed/ag-rated), GFCI receptacles, switches, fan circuits, exterior lights
Electrical permit and licensed contractor named
Water line: source (well / rural water / house), depth (≥36 in here), length
Frost-free hydrants (count, inside/outside)
Wash-stall plumbing and water heater
Septic or drain for wash water / bathroom (permit required?)
Plumbing permit and licensed contractor named
Utilities subtotal

F. Engineering, permits and paperwork

Line Bid 1 Bid 2 Bid 3
Who pulls the building/zoning permit
Permit fees included or passed through
Agricultural-exemption or use affidavit handled by
Site plan / boundary survey requirement handled by
Land-disturbance or floodplain permit (if ≥1 acre disturbed or in floodplain)
Entrance / driveway permit
811 locates scheduled by

G. Schedule and terms

Line Bid 1 Bid 2 Bid 3
Start window (month) and total duration
Sequence stated (engineering → permit → pad → erect → concrete → stalls → trades)
Payment schedule (e.g., deposit / at start / at completion)
Price validity (days) and materials-escalation clause
Change-order pricing method
Warranties: structure, roof/wall steel paint, workmanship (years, who honors)
Insurance: general liability and workers' comp certificates offered
References, or a visit to a completed barn, if offered

H. The two lines that matter most

Bid 1 Bid 2 Bid 3
Total as written
Total after you fill every "excluded" line with a real number

Compare the second row only. The cost guide gives sourced ranges for filling the blanks; the planning guide explains what each line should say. When you are ready for a proposal that comes with every line already filled in, request one here.